[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108610":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108610,783,1,"单选题","在工程网络计划中，如果某项工作的最早开始时间和最早完成时间分别为2天和6天，则该工作实际上最早应从开工后（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","第2天上班时刻开始，第6天下班时刻完成",false,{"key":16,"text":17,"correct":14},"B","第2天上班时刻开始，第7天下班时刻完成",{"key":19,"text":20,"correct":21},"C","第3天上班时刻开始，第6天下班时刻完成",true,{"key":23,"text":24,"correct":14},"D","第3天上班时刻开始，第7天下班时刻完成","考点:双代号网络计划时间参数的计算。网络计划时间参数中的开始时间和完成时间都应以时间单位的终了时刻为标准。第2天开始即是指第2天终了（下班）时刻开始，实际上是第3天上班时刻开始；第6天完成即是指第6天终了（下班）时刻完成。参见教材P46。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]