[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108609":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108609,783,1,"单选题","某工程双代号网络计划如下图所示，图中已标出的各个节点的最早时间和最迟时间，该计划表明（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作1-2的自由时差为2",false,{"key":16,"text":17,"correct":18},"B","工作2-5的总时差为7",true,{"key":20,"text":21,"correct":14},"C","工作4-6的总时差为零",{"key":23,"text":24,"correct":14},"D","工作3-5为关键工作","考点:双代号网络计划时间参数的计算。关键线路为①→③→④→⑤→⑥。选项A错误，工作1-2的自由时差=4-0-4=0；选项C错误，工作4-6的总时差=21-14-5=2；选项D错误，工作3-5不是关键工作。参见教材P53。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]