[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108608":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108608,783,1,"单选题","某工程双代号网络计划如图所示，其中E工作的最早开始时间和最迟开始时间是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3和5",false,{"key":16,"text":17,"correct":14},"B","3和6",{"key":19,"text":20,"correct":21},"C","4和5",true,{"key":23,"text":24,"correct":14},"D","4和6","考点:双代号网络计划时间参数的计算。关键线路：①→②→⑥→⑧和①→③→⑦→⑧。E工作的最早开始时间等于其紧前工作最早完成时间的最大值，最迟开始时间等于其紧后工作最迟开始时间的最小值减去本工作的持续时间。计算工期=3+6+5=14，E工作最早开始时间=max{3，2，4}=4，最迟开始时间=min{14-5，14-4，14-6}-3=8-3=5。参见教材P46。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]