[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108602":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108602,783,1,"单选题","某工程双代号时标网络计划如下图所示，其中工作G的总时差为（ ）周。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":21},"C","4",true,{"key":23,"text":24,"correct":14},"D","5","考点:时标网络计划中时间参数的判定。总时差等于其紧后工作的总时差加本工作与其紧后工作之间的时间间隔所得之和的最小值，即：TFG＝min{TFJ＋LAGG，J}=2＋2=4（周）。参见教材P63",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]