[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108601,783,1,"单选题","某工程双代号时标网络计划如下图所示，如果其中的 B、C和G三项工作共用一台施工机械而必须顺序施工，则在不影响总工期及工作工艺关系的前提下，该施工机械在施工现场的最小闲置时间是（ ）周。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",true,{"key":16,"text":17,"correct":18},"B","2",false,{"key":20,"text":21,"correct":18},"C","3",{"key":23,"text":24,"correct":18},"D","4","考点:时标网络计划中时间参数的判定。工作B在第1周末开始，第3周末结束；工作C在第4周末开始，第8周末结束；工作G在第8周末开始，第10周末结束，闲置一周。参见教材P62",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]