[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108599":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108599,783,1,"单选题","某工程双代号时标网络计划如下图所示，如果 B、 D、I三项工作共用一台施工机械且必须顺序施工，则总工期（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","会延长2周，但施工机械在现场不会闲置",false,{"key":16,"text":17,"correct":14},"B","会延长2周，且施工机械会在现场闲置6周",{"key":19,"text":20,"correct":21},"C","不会延长，且施工机械在现场也不会闲置",true,{"key":23,"text":24,"correct":14},"D","不会延长，但施工机械会在现场闲置2周","考点:时标网络计划中时间参数的判定。D工作为关键工作，B工作第3周末完成，I工作第9周末开始，机械不会闲置。参见教材P63。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]