[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108598":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108598,783,1,"单选题","不能示出整个工程的开工日期和完工日期以及各项工作的开始日期和完成日期的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计算坐标体系",false,{"key":16,"text":17,"correct":18},"B","工作日坐标体系",true,{"key":20,"text":21,"correct":14},"C","日历坐标体系",{"key":23,"text":24,"correct":14},"D","时间坐标体系","考点:时标网络计划的坐标体系。工作日坐标体系可明示各项工作在整个工程开工后第几天（上班时刻）开始和第几天（下班时刻）完成，但不能示出整个工程的开工日期和完工日期以及各项工作的开始日期和完成日期。参见教材P64。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]