[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108597":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108597,783,1,"单选题","编制时标网络计划时，间接绘制法是指（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","不计算时间参数而直接按无时标的网络计划草图绘制时标网络计划",false,{"key":16,"text":17,"correct":14},"B","计算时间参数而直接按无时标的网络计划草图绘制时标网络计划",{"key":19,"text":20,"correct":14},"C","不计算时间参数而直接按有时标的网络计划草图绘制时标网络计划",{"key":22,"text":23,"correct":24},"D","根据无时标的网络计划草图在时标网络计划表中进行绘制",true,"考点:时标网络计划的编制方法。间接绘制法是指先根据无时标的网络计划草图，计算其时间参数，并确定关键线路，然后在时标网络计划表中进行绘制。参见教材P60。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]