[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108595":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108595,783,1,"单选题","某工程双代号网络计划中，工作N的持续时间为4天，相关节点的最早时间和最迟时间如下图所示，则工作N的自由时差是（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":21},"C","3",true,{"key":23,"text":24,"correct":14},"D","4","考点:节点法。工作N的自由时差FFM=9-4-2=3天。参见教材P50",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]