[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108594":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108594,783,1,"单选题","工程网络计划工期优化过程中，首先应选择压缩持续时间的工作是（ ）的关键工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","缩短时间对质量和安全影响不大",true,{"key":16,"text":17,"correct":18},"B","工程变更程序相对简单",false,{"key":20,"text":21,"correct":18},"C","资源消耗比较均衡",{"key":23,"text":24,"correct":18},"D","直接成本最小","考点:工期优化。选择压缩对象时宜在关键工作中考虑下列因素：（1）缩短持续时间对质量和安全影响不大的工作；（2）有充足备用资源的工作；（3）缩短持续时间所需增加的费用最少的工作。参见教材P66",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]