[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108593":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108593,783,1,"单选题","当工程网络计划的计算工期大于要求工期时，为满足要求工期，进行工期优化的基本方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","减少相邻工作之间的时间间隔",false,{"key":16,"text":17,"correct":18},"B","缩短关键工作的持续时间",true,{"key":20,"text":21,"correct":14},"C","减少相邻工作之间的时距",{"key":23,"text":24,"correct":14},"D","缩短关键工作的总时差","考点:工期优化。网络计划工期优化的基本方法是在不改变网络计划中各项工作之间逻辑关系的前提下，通过压缩关键工作的持续时间来达到优化目标。参见教材P66。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]