[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108591":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108591,783,1,"单选题","网络计划的费用优化压缩被压缩对象到（ ）为止。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接费用率或组合大于工程间接费用率",true,{"key":16,"text":17,"correct":18},"B","直接费用率或组合小于工程间接费用率",false,{"key":20,"text":21,"correct":18},"C","直接费用率或组合等于工程间接费用率",{"key":23,"text":24,"correct":18},"D","直接费用率或组合最小","考点:费用优化。如果被压缩对象的直接费用率或组合直接费用率大于工程间接费用率，说明压缩关键工作的持续时间会使工程总费用增加，此时应停止缩短关键工作的持续时间，在此之前的方案即为优化方案。参见教材P71。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]