[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108588":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108588,783,1,"单选题","停止费用优化时，应满足的要求是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","压缩对象的直接费用率或组合直接费用率大于工程间接费用率",true,{"key":16,"text":17,"correct":18},"B","压缩对象的直接费用率或组合直接费用率小于工程间接费用率",false,{"key":20,"text":21,"correct":18},"C","压缩对象的直接费用率或组合直接费用率等于工程间接费用率",{"key":23,"text":24,"correct":18},"D","压缩对象的直接费用率或组合直接费用率与工程间接费用率没有关系","考点:费用优化。根据费用优化的方法，重复对各工作进行压缩，直至计算工期满足要求工期或被压缩对象的直接费用率或组合直接费用率大于工程间接费用率为止。参见教材P71",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]