[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108586":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108586,783,1,"单选题","工程网络计划费用优化过程中，压缩关键工作的持续时间应遵循的基本原则是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","必须将关键工作压缩成非关键工作",false,{"key":16,"text":17,"correct":14},"B","压缩后工作的持续时间不能小于其总时差",{"key":19,"text":20,"correct":14},"C","优先选择压缩综合费率最小的关键工作",{"key":22,"text":23,"correct":24},"D","多条关键线路的持续时间应压缩相同数值",true,"考点:费用优化。当只有一条关键线路时，应找出直接费用率最小的一项关键工作，作为缩短持续时间的对象；当有多条关键线路时，应找出组合直接费用率最小的一组关键工作，作为缩短持续时间的对象。当需要缩短关键工作的持续时间时，其缩短值的确定必须符合下列两条原则：缩短后工作的持续时间不能小于其最短持续时间；缩短持续时间的工作不能变成非关键工作。参见教材P71。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]