[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108585":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108585,783,1,"单选题","关于工程网络计划费用优化的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","缩短持续时间的工作不能变成非关键工作",true,{"key":16,"text":17,"correct":18},"B","缩短持续时间的工作应为直接费最小的关键工作",false,{"key":20,"text":21,"correct":18},"C","必要时可调整关键工作之间的逻辑关系",{"key":23,"text":24,"correct":18},"D","工程总费用会随着工期的缩短而增加","考点:费用优化。当需要缩短关键工作的持续时间时，其缩短值的确定必须符合下列两条原则：（1）缩短后工作的持续时间不能小于其最短持续时间；（2）缩短持续时间的工作不能变成非关键工作。参见教材P71",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]