[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108584":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108584,783,1,"单选题","建设工程多级网络计划系统的编制应采用（ ）的方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自下向上.分级编制",false,{"key":16,"text":17,"correct":18},"B","自顶向下.分级编制",true,{"key":20,"text":21,"correct":14},"C","自顶向下.整体编制",{"key":23,"text":24,"correct":14},"D","自下向上.整体编制","考点:多级网络计划。多级网络计划系统的编制必须采用自顶向下、分级编制的方法。参见教材P85。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]