[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108582,783,1,"单选题","下列关于双代号网络图与单代号网络图的描述正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","双代号网络图的虚箭线不消耗资源",true,{"key":16,"text":17,"correct":18},"B","单代号网络图的箭线不能反映工作之间的逻辑关系",false,{"key":20,"text":21,"correct":18},"C","单代号网络图中可能出现虚箭线",{"key":23,"text":24,"correct":18},"D","双代号网络图的箭线不消耗时间","考点:单代号网络图的绘制。选项B错误，单代号网络图的箭线反映工作之间的逻辑关系；选项C错误，单代号网络图中可能出现虚工作，不会出现虚箭线；选项D错误，双代号网络图的箭线消耗时间。参见教材P43",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]