[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108580":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108580,783,1,"单选题","单代号网络计划中工作与其紧后工作之间的时间间隔应等于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","其紧后工作的最早开始时间与该工作的最早开始时间之差",false,{"key":16,"text":17,"correct":18},"B","其紧后工作的最早开始时间与该工作的最早完成时间之差",true,{"key":20,"text":21,"correct":14},"C","其紧后工作的最迟开始时间与该工作的最迟完成时间之差",{"key":23,"text":24,"correct":14},"D","其紧后工作的最早完成时间与该工作的最早完成时间之差","考点:单代号网络计划时间参数的计算。相邻两项工作之间的时间间隔是指其紧后工作的最早开始时间与本工作最早完成时间的差值，即：LAGi，j＝ESj－EFi。参见教材P56",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]