[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108577":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108577,783,1,"单选题","如果在搭接网络计划中出现EFj>（EFi+FTFi，j）的情况下，说明（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作i和工作j之间存在时间间隔LAGi，j",true,{"key":16,"text":17,"correct":18},"B","工作i和工作j之间不存在时间间隔LAGi，j",false,{"key":20,"text":21,"correct":18},"C","相邻两项工作之间不存在搭接关系",{"key":23,"text":24,"correct":18},"D","相邻两项工作之间存在两种时距","考点:单代号搭接网络计划。如果在搭接网络计划中出现EFj>（EFi+FTFi，j）的情况时，就说明在工作i和工作j存在时间间隔LAGi，j。参见教材P83",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]