[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108575":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108575,783,1,"单选题","某分部工程单代号搭接网络计划如下图所示，其中关键工作是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工作A和工作B",false,{"key":16,"text":17,"correct":14},"B","工作B和工作D",{"key":19,"text":20,"correct":14},"C","工作C和工作E",{"key":22,"text":23,"correct":24},"D","工作C和工作D",true,"考点:单代号搭接网络计划。单代号搭接网络计划可以利用相邻两项工作之间的时间间隔来判定关键线路。即从搭接网络计划的终点节点开始，逆着箭线方向依次找出相邻两项工作之间的时间间隔为零的线路就是关键线路。本题需要虚拟一项开始工作S，关键线路为S→C→D→F。参见教材P81。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]