[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108573":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108573,783,1,"单选题","单代号搭接网络计划中，计算相邻两项工作之间的时间间隔，当EFj>（ESi+STFi，j）时距时，（ ），可以断定工作i和工作j存在时间间隔LAGi，j。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","搭接关系为FTS",false,{"key":16,"text":17,"correct":14},"B","搭接关系为STS",{"key":19,"text":20,"correct":14},"C","搭接关系为FTF",{"key":22,"text":23,"correct":24},"D","搭接关系为STF",true,"考点:单代号搭接网络计划。搭接关系为开始到结束（STF）时的时间间隔，如果在搭接网络计划中出现EFj>（ESi+STFi，j）的情况时，就说明在工作i和工作j存在时间间隔LAGi，j。参见教材P80",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]