[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108566":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108566,783,1,"单选题","某工程单代号搭接网络计划中工作 B、 D、E之间的搭接关系和时间参数如下图所示。工作D和工作E的总时差分别为6天和2天，则工作B的总时差为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","8",{"key":19,"text":20,"correct":21},"C","9",true,{"key":23,"text":24,"correct":14},"D","12","考点:搭接网络计划时间参数的计算。工作B的总时差=min{6+3,2+8}=9天。参见教材P82。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]