[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108565":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108565,783,1,"单选题","在工程网络计划中，关键工作是指（ ）的工作。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","双代号时标网络计划中无波形线",false,{"key":16,"text":17,"correct":14},"B","双代号网络计划中开始节点为关键节点",{"key":19,"text":20,"correct":21},"C","最迟完成时间与最早完成时间的差值最小",true,{"key":23,"text":24,"correct":14},"D","单代号搭接网络计划中时距最小","考点:关键线路和关键工作的确定方法。在网络计划中，总时差最小的是关键线路。工作的总时差等于该工作最迟完成时间与最早完成时间之差，或该工作最迟开始时间与最早开始时间之差。参见教材P48。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]