[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108563":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108563,783,1,"单选题","关于多级网络计划系统的编制，说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","自顶向下逐层编制，先总体、再局部、后细部",false,{"key":16,"text":17,"correct":14},"B","分级的多少应视工程规模、复杂程度及组织管理的需要而定",{"key":19,"text":20,"correct":14},"C","分级编制网络计划应与科学编码相结合，以便于利用计算机进行绘图、计算和管理",{"key":22,"text":23,"correct":24},"D","总体计划应由管理层编制",true,"考点:多级网络计划系统。选项D，在多级网络计划系统中，总体网络计划由决策层编制；局部网络计划由管理层编制。参见教材P85。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]