[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108562":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108562,783,1,"单选题","某工程单代号搭接网络计划如下图所示，其中B和D工作的最早开始时间是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","4和4",false,{"key":16,"text":17,"correct":14},"B","6和7",{"key":19,"text":20,"correct":21},"C","2和0",true,{"key":23,"text":24,"correct":14},"D","2和2","考点:搭接网络计划时间参数的计算。工作B最早开始时间是2，工作D最早开始时间是0。参见教材P82。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]