[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108557":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108557,783,1,"单选题","在单代号网络计划中，关键线路是指（ ）的线路。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","各项工作持续时间之和最小",false,{"key":16,"text":17,"correct":14},"B","由关键工作组成",{"key":19,"text":20,"correct":21},"C","相邻两项工作之间时间间隔均为零",true,{"key":23,"text":24,"correct":14},"D","各项工作自由时差均为零","考点:关键线路和关键工作的确定方法。在单代号网络计划中，关键线路是指相邻两项工作之间时间间隔均为零的线路。参见教材P59。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]