[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108554":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108554,783,1,"单选题","工程网络计划的工期优化是指通过（ ）而使计算工期满足要求工期。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","压缩关键工作的持续时间",true,{"key":16,"text":17,"correct":18},"B","改变关键工作之间的逻辑关系",false,{"key":20,"text":21,"correct":18},"C","压缩资源需求量小的工作的持续时间",{"key":23,"text":24,"correct":18},"D","减少非关键工作的自由时差","考点:工期优化。网络计划工期优化的基本方法是在不改变网络计划中各项工作之间逻辑关系的前提下，通过压缩关键工作的持续时间来达到优化目标。参见教材P66。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]