[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108553":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108553,783,1,"单选题","当工程网络计划的工期优化过程中出现多条关键线路时，必须（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","将持续时间最长的关键工作压缩为非关键工作",false,{"key":16,"text":17,"correct":14},"B","压缩各条关键线路上直接费最小的工作的持续时间",{"key":19,"text":20,"correct":14},"C","压缩各条关键线路上持续时间最长的工作的持续时间",{"key":22,"text":23,"correct":24},"D","将各条关键线路的总持续时间压缩相同数值",true,"考点:工期优化。当工期优化过程中出现多条关键线路时，必须将各条关键线路的总持续时间压缩相同数值。参见教材P66。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]