[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108552":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108552,783,1,"单选题","网络计划工期优化方法中，通过压缩关键工作的持续时间来达到优化目标的前提是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计算工期不满足计划工期",false,{"key":16,"text":17,"correct":18},"B","不改变各项工作之间的逻辑关系",true,{"key":20,"text":21,"correct":14},"C","计划工期不满足计算工期",{"key":23,"text":24,"correct":14},"D","将关键工作压缩成非关键工作","考点:工期优化。网络计划工期优化的基本方法是在不改变网络计划中各项工作之间的逻辑关系的前提下，通过压缩关键工作的持续时间来达到优化目标。参见教材P66。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]