[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108551":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108551,783,1,"单选题","对下面双代号网络图进行工期优化，当各工作压缩费率如下所示时，欲压缩总工期1天，应当选择（ ）进行压缩。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工作A",false,{"key":16,"text":17,"correct":14},"B","工作B",{"key":19,"text":20,"correct":21},"C","工作C",true,{"key":23,"text":24,"correct":14},"D","工作D","考点:工期优化。关键线路：B-C-G。其中费率最低的是工作C，所以答案为选项C。参见教材P66。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]