[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108550":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108550,783,1,"单选题","在费用优化时，如果被压缩对象的直接费用率或组合直接费用率等于工程间接费用率时，（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应压缩关键工作的持续时间",true,{"key":16,"text":17,"correct":18},"B","应压缩非关键工作的持续时间",false,{"key":20,"text":21,"correct":18},"C","停止缩短关键工作的持续时间",{"key":23,"text":24,"correct":18},"D","停止缩短非关键工作的持续时间","考点:费用优化。如果被压缩对象的直接费用率或组合费用率等于工程间接费用率时，说明压缩关键工作的持续时间不会使工程总费用增加，故应缩短关键工作的持续时间。参见教材P70。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]