[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108547":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108547,783,1,"单选题","在网络计划的费用优化过程中，缩短持续时间的工作应是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接费用率最小的关键工作",true,{"key":16,"text":17,"correct":18},"B","直接费用率最大的关键工作",false,{"key":20,"text":21,"correct":18},"C","直接费用率最小的非关键工作",{"key":23,"text":24,"correct":18},"D","直接费用率最大的非关键工作","考点:费用优化。在网络计划的费用优化过程中，缩短持续时间的工作应是直接费用率最小的关键工作。参见教材P70。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]