[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108544":3},{"question":4,"library":22},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":15,"analysis":21},1108544,783,1,"单选题","已知网络计划如下图所示，箭线上方括号外为工作名称，括号内为优先压缩顺序；箭线下方括号外为正常持续时间，括号内为最短持续时间，若对其工期进行压缩，应首先压缩工作（ ）。",[11,14,17,19],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":16},"B",true,{"key":18,"text":18,"correct":13},"C",{"key":20,"text":20,"correct":13},"D","考点:工期优化的方法。通过标号法可以得出关键线路为B→G→I。选择缩短关键工作的持续时间来进行，所以首先选择工作B、G、I进行压缩，这三项工作中工作B的优先压缩顺序最靠前，所以首先压缩工作B。参见教材P66。",{"id":6,"name":23,"category":24,"favorite":25},"目标控制（土木建筑）","建筑工程",0]