[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108541":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108541,783,1,"单选题","双代号时标网络计划中，以终点节点为完成节点的工作除外，当计划工期等于计算工期时，这些工作箭线中波形线的水平投影长度表示其（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总时差",false,{"key":16,"text":17,"correct":18},"B","自由时差",true,{"key":20,"text":21,"correct":14},"C","间歇时间",{"key":23,"text":24,"correct":14},"D","搭接时间","考点:时标网络计划中工作六个时间参数的判定。以终点节点为完成节点的工作除外，当计划工期等于计算工期时，这些工作的自由时差就是该工作箭线中波形线的水平投影长度。参见教材P62。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]