[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108540":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108540,783,1,"单选题","双代号时标网络计划中，当某工作之后有虚工作时，则该工作的自由时差为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","该工作的波形线的水平长度",false,{"key":16,"text":17,"correct":18},"B","本工作与紧后工作间波形线水平长度和的最小值",true,{"key":20,"text":21,"correct":14},"C","本工作与紧后工作间波形线水平长度和的最大值",{"key":23,"text":24,"correct":14},"D","后续所有线路段中波形线中水平长度和的最小值","考点:双代号时标网络计划工作总时差和自由时差的判定。时标网络计划中应以实箭线表示工作，虚箭线表示虚工作，以波形线表示工作的自由时差。参见教材P62。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]