[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108539":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108539,783,1,"单选题","某双代号网络计划中，已知工作A的紧后工作是B和 C，工作B的最迟开始时间为第14天，最早开始时间为第10天；工作C的最迟完成时间为第16天，最早完成时间为第14天；工作A的自由时差为5天，则工作A的总时差为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":18},"B","7",true,{"key":20,"text":21,"correct":14},"C","9",{"key":23,"text":24,"correct":14},"D","11","考点:双代号网络计划时间参数的计算。工作B的总时差=14-10=4（天），工作C的总时差=16-14=2（天），工作A的总时差=5+min{4，2}=7（天）。参见教材P62。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]