[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108538":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108538,783,1,"单选题","在下图的双代号时标网络计划中，如果 A、 E、G三项工作共用一台施工机械而必须顺序施工，则该施工机械在现场的最小闲置时间为（ ）周。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",true,{"key":16,"text":17,"correct":18},"B","2",false,{"key":20,"text":21,"correct":18},"C","3",{"key":23,"text":24,"correct":18},"D","4","考点:双代号时标网络计划工作总时差和自由时差的判定。关键线路：A-D-H。施工机械在现场的最小闲置时间为1周。参见教材P62。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]