[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108537":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108537,783,1,"单选题","在工程网络计划中，某项工作的最迟开始时间与最早开始时间的差值为该工作的（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","时间间隔",false,{"key":16,"text":17,"correct":14},"B","搭接时距",{"key":19,"text":20,"correct":14},"C","自由时差",{"key":22,"text":23,"correct":24},"D","总时差",true,"考点:双代号网络计划时间参数的计算。某项工作的最迟开始时间与最早开始时间的差值为该工作的总时差。参见教材P45。 新 版 习 题，考 前 押 题，金 考 典 软 件 考 前 更 新，下 载 链 接 w w w. j i n k a o d i a n . c o m",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]