[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108536":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108536,783,1,"单选题","最迟完成时间是指（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在紧前工作的约束下，本工作有可能完成的最迟时刻",false,{"key":16,"text":17,"correct":14},"B","在紧后工作的约束下，本工作有可能完成的最迟时刻",{"key":19,"text":20,"correct":14},"C","在后续工作的约束下，本工作必须完成的最迟时刻",{"key":22,"text":23,"correct":24},"D","在总工期的约束下，本工作必须完成的最迟时刻",true,"考点:双代号网络计划时间参数的计算。最迟完成时间是指在总工期的约束下，本工作必须完成的最迟时刻。参见教材P45。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]