[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108534":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108534,783,1,"单选题","在工程网络计划中，工作的最早开始时间应为其所有紧前工作（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","最早开始时间的最大值",false,{"key":16,"text":17,"correct":14},"B","最早开始时间的最小值",{"key":19,"text":20,"correct":21},"C","最早完成时间的最大值",true,{"key":23,"text":24,"correct":14},"D","最早完成时间的最小值","考点:双代号网络计划时间参数的计算。工作的最早开始时间等于其紧前工作最早完成时间的最大值。参见教材P45。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]