[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108533":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108533,783,1,"单选题","在工程网络计划中，工作的最迟开始时间等于本工作的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最迟完成时间与其时间间隔之差",false,{"key":16,"text":17,"correct":18},"B","最迟完成时间与其持续时间之差",true,{"key":20,"text":21,"correct":14},"C","最早开始时间与其持续时间之和",{"key":23,"text":24,"correct":14},"D","最早开始时间与其时间间隔之和","考点:双代号网络计划时间参数的计算。工作的最迟开始时间等于本工作的最迟完成时间和其持续时间之差。LSi－j=LFi－j－Di－j。参见教材P45。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]