[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108532":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108532,783,1,"单选题","在工程网络计划中，某项工作的最早完成时间与其紧后工作的最早开始时间之间的差值称为这两项工作之间的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","时间间隔",true,{"key":16,"text":17,"correct":18},"B","间歇时间",false,{"key":20,"text":21,"correct":18},"C","自由时差",{"key":23,"text":24,"correct":18},"D","时距","考点:双代号网络计划时间参数的计算。某项工作的最早完成时间与其紧后工作的最早开始时间之间的差值称为这两项工作之间的时间间隔。参见教材P45。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]