[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108529":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108529,783,1,"单选题","某工程双代号网络计划如图所示，其中E工作的最早开始时间和最迟开始时间是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3和5",false,{"key":16,"text":17,"correct":14},"B","3和6",{"key":19,"text":20,"correct":21},"C","4和5",true,{"key":23,"text":24,"correct":14},"D","4和6","考点:标号法。关键线路：①→②→⑥→⑧和①→③→⑦→⑧。计算工期=3+6+5=14，E工作最早开始时间是4，最迟开始时间是5。参见教材P54。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]