[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108528":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108528,783,1,"单选题","某工程单代号网络计划如下图所示（时间单位：天），下列说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作E是关键工作",true,{"key":16,"text":17,"correct":18},"B","工作B的自由时差为0",false,{"key":20,"text":21,"correct":18},"C","工作D的总时差为2天",{"key":23,"text":24,"correct":18},"D","工作F的最迟开始时间为22天","考点:单代号网络计划有关时间参数的计算。经计算可知关键线路为A→C→G→H；工作F的最迟开始时间为22天；工作D的总时差为2天；工作B的自由时差为0；工作E为非关键工作。参见教材P55。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]