[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108522":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108522,783,1,"单选题","在不影响其紧后工作最早开始时间的前提下，本工作可利用的机动时间为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总时差",false,{"key":16,"text":17,"correct":14},"B","最迟开始时间",{"key":19,"text":20,"correct":21},"C","自由时差",true,{"key":23,"text":24,"correct":14},"D","最迟完成时间","考点:双代号网络计划时间参数的计算。在不影响其紧后工作最早开始时间的前提下，本工作可利用的机动时间为自由时差。参见教材P45。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]