[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108519":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108519,783,1,"单选题","某工作有且仅有两个紧后工作 C、 D，其中C工作最早开始时间为10（计算坐标系,下同），最迟完成时间为28，持续时间为15天；D工作最早完成时间为18，最迟完成时间为20，持续时间为6天；该工作与C工作间的时间间隔为2天，与D工作间的时间间隔为4天，则该工作的总时差为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":21},"C","5",true,{"key":23,"text":24,"correct":14},"D","6","考点:单代号网络计划有关时间参数的计算。工作C的总时差=28-（10+15）=3天，工作D的总时差=20-18=2天。该工作的总时差＝min{3+2，2+4}=5天。参见教材P55。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]