[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108517":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108517,783,1,"单选题","某双代号网络计划中，工作M的最早开始时间和最迟开始时间分别为第12天和第17天，其持续时间为5天。工作M有3项紧后工作，它们的最早开始时间分别为第21天、第24天和第28天，则工作M的自由时差和总时差分别为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1，4",false,{"key":16,"text":17,"correct":14},"B","3，3",{"key":19,"text":20,"correct":21},"C","4；5",true,{"key":23,"text":24,"correct":14},"D","5；5","考点:标号法。总时差=17-12=5天；自由时差=min{21、24、28}-12=21-（12+5）=4天。参见教材P54。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]