[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108514":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108514,783,1,"单选题","（ ）方式是组织几个劳动组织相同的工作队，在同一时间、不同的空间，按施工工艺要求完成各施工对象。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","依次施工",false,{"key":16,"text":17,"correct":18},"B","平行施工",true,{"key":20,"text":21,"correct":14},"C","流水施工",{"key":23,"text":24,"correct":14},"D","分段施工","考点:流水施工方式。平行施工方式是组织几个劳动组织相同的工作队，在同一时间、不同的空间，按施工工艺要求完成各施工对象。参见教材P21。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]