[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108513":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108513,783,1,"单选题","在下列施工组织方式中，不能实现工作专业化施工的组织方式是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","依次施工和平行施工",true,{"key":16,"text":17,"correct":18},"B","平行施工和流水施工",false,{"key":20,"text":21,"correct":18},"C","搭接施工和平行施工",{"key":23,"text":24,"correct":18},"D","依次施工和流水施工","考点:流水施工方式。流水施工，各工作队实现了专业化施工，有利于提高技术水平和劳动生产率。依次施工和平行施工不能实现工作专业化施工。参见教材P21",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]