[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108512":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108512,783,1,"单选题","关于平行施工组织方式的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","专业工作队能够保持连续施工",false,{"key":16,"text":17,"correct":14},"B","单位时间内投入的资源量较均衡",{"key":19,"text":20,"correct":21},"C","能充分利用工作面且工期短",true,{"key":23,"text":24,"correct":14},"D","专业工作队能够最大限度地搭接施工","考点:流水施工方式。选项A错误，专业工作队不能够保持连续施工；选项B错误，单位时间内投入的劳动力、施工机具、材料等资源量成倍地增加；选项D错误，专业工作队不能够最大限度地搭接施工。参见教材P21。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]